Garfield Township, Michigan, unanimously approved a one-year moratorium on data centers and cryptocurrency mining facilities, with an option to extend six more months, after residents packed a July zoning meeting over concerns about water, electric rates, and environmental impact.
Township officials say the pause, built through a zoning ordinance amendment rather than a standalone resolution, is meant to withstand legal challenges that have sunk similar bans elsewhere.
The move likely stalls a proposal from an Illinois developer to convert a Cass Road building into a small-scale data center, and joins a wave of similar bans across northern Michigan townships, even as state law forbids outright banning a land use.
The full dispatch is available from the source below.